Set up manufacturing

Docs › Setup guides

ERPNext Manufacturing Setup

ERPNext manufacturing setup, step by step: settings, workstations, operations, routing, multi-level BOMs, production plan, work orders, job cards and costs.

5 min read · Updated November 2026 · By Vivek Choudhary

This guide walks you through the ERPNext manufacturing setup in the order that works best. You start with settings and masters, build your BOMs, and then run one full production cycle from plan to finished goods. If you want an overview first, read ERPNext Manufacturing explained.

Before you start

  • Your company, chart of accounts and fiscal year are set up.
  • Items exist for finished goods, sub-assemblies and raw materials, with the correct unit of measure. Raw materials have "Maintain Stock" ticked.
  • You have warehouses for raw materials, work in progress (WIP), finished goods and scrap.
  • Opening stock of raw materials is entered, so transfers do not fail.
  • You have a written list of the steps (operations) each product goes through and the machines or areas used.

Step-by-step setup

  1. Manufacturing > Settings > Manufacturing Settings. Set the Default Work In Progress Warehouse, Default Finished Goods Warehouse and Default Scrap Warehouse. Choose Backflush Raw Materials Based On: "BOM" consumes the BOM quantities; "Material Transferred for Manufacture" consumes what was actually moved. Decide whether to allow overproduction (Overproduction Percentage For Work Order) and whether Update BOM Cost Automatically should be on. Leave capacity planning on if you want work orders scheduled against workstation hours.
  2. Workstation list > New. Create one workstation per machine or work area. Fill the Operating Costs table (for example electricity, rent, consumables, wages), the Working Hours table with shift times, a Holiday List, and Production Capacity (how many jobs it can run at the same time).
  3. Operation list > New. Create each step such as cutting, welding or packing, and set its default workstation.
  4. Routing list > New (optional). A routing is a reusable sequence of operations. Add rows with Sequence ID, Operation, Workstation and Operation Time in minutes. The sequence ID stops a later operation from being completed before an earlier one.
  5. Manufacturing > Bill of Materials > Bill of Materials > New. Select the Item and the Quantity this BOM produces. In the items table add each raw material with its qty and source warehouse. Tick With Operations if you want operation costs and job cards, then pick a routing or add operations by hand. Set Rate Of Materials Based On (Valuation Rate, Last Purchase Rate or Price List). Mark it Is Active and Is Default, then submit.
  6. Multi-level BOMs. Create and submit BOMs for sub-assemblies first, then add the sub-assembly as a row in the parent BOM; its default BOM is fetched. The Materials Required (Exploded) table shows all raw materials down the tree. Tick Do Not Explode on a row if you keep that sub-assembly in stock and do not want it broken down.
  7. Scrap and process loss. In the BOM's scrap section, add scrap items with quantity and rate if they have resale value. If some of the finished item itself is lost in the process, add the same item as scrap; ERPNext treats it as process loss and reduces the output. (In newer versions this table may be labelled differently, such as Secondary Items.)
  8. Manufacturing > Production > Production Plan > New. Set Get Items From to Sales Order or Material Request, click Get Sales Orders (or Get Material Request), then Get Items for Work Order. Click Get Sub Assembly Items and choose the Manufacturing Type for each (In House, Subcontract or Material Request). In material planning, use Get Items for Purchase Only or Get Items for Purchase / Transfer, and tick Skip Available Raw Materials if you only want to buy what is short. Submit, then use the create buttons to make Work Orders and Material Requests.
  9. Manufacturing > Production > Work Order. Check the item, BOM, quantity and Planned Start Date. Fill the Source Warehouse, WIP Warehouse, Target Warehouse and, if needed, Scrap Warehouse. Warehouses are required before you submit. Submit the work order.
  10. Material transfer. On the work order click Start, enter the quantity and submit the "Material Transfer for Manufacture" stock entry. This moves raw materials to the WIP warehouse. Only items with "Include Item In Manufacturing" are transferred.
  11. Manufacturing > Production > Job Card. For each operation, the shop floor clicks Start Job, picks the employee, and later clicks Complete Job with the Completed Quantity. You can also type From Time, To Time and Completed Qty in the Time Logs table. Submit the job card when done.
  12. Finish. Back on the work order, click Finish and enter the quantity made. ERPNext creates a Manufacture stock entry that consumes the raw materials and adds finished goods (and scrap) to their warehouses. You can finish in parts.

Cost check

Before you trust the numbers, compare three costs for one finished item:

WhereWhat it showsWhat to look for
BOM (cost section)Planned raw material, operating and scrap costRates are realistic; use Update Cost if prices changed
Manufacture stock entryActual cost of materials consumed plus additional costsValuation rate of the finished item is close to the BOM cost
Stock Ledger for the finished itemIncoming rate after each manufactureNo zero or unusually high rates

Big gaps usually mean wrong BOM quantities, missing operating costs on workstations, or raw materials with a zero valuation rate.

Check your work

  • Run one test order end to end in a test site before going live.
  • Raw material stock dropped by the expected quantity, and finished goods stock went up.
  • The WIP warehouse is empty once the work order is completed.
  • Job cards show time for every operation and the work order status is "Completed".
  • The production plan shows the right shortages and the material requests match them.

Common mistakes

  • BOM quantity left at 1 when the recipe is written for a batch. Every quantity is then wrong.
  • Sub-assembly BOMs not submitted or not set as default, so the parent BOM fetches nothing.
  • Raw materials with no opening stock or no valuation rate, which blocks transfers or gives zero cost.
  • Workstations without operating costs, so labour and machine cost never reach the product.
  • Editing a submitted BOM. You cannot; cancel it or duplicate it, change the copy and submit it as the new default.
  • Using manufacturing for work done by a vendor. Use Subcontracting instead.

Sources

Written from the official documentation and source code below. Menus and fields can differ between versions, so check the docs for your version.

Planning ERPNext or a Frappe app for your business? See our ERPNext implementation and Frappe development services, or talk to us.
ERPWork app icon
ERPWork: ERPNext on your phoneFree Android app for your ERPNext site: check in with location, approve documents, see sales and stock dashboards and get notifications.

Get it on Google PlayLearn more →